Bio-mass boiler touted as boon to area
February 28, 2007
Duane Hicks
Staff writer
FORT FRANCESWill the Fort Frances mill get the bio-mass boiler or not?
Mill workers and area residents alike will find out the answer to that
question very shortly as the proposal will go before Abitibi-Consolidateds
board of directors for approval March 6.
If the $84.3-million project is approved, work will begin almost
immediately, with the new boiler targeted to be up and running by October,
2008.
And with it will come not only long-term viability for the paper mill
here, but benefits to the local economy, regional manager Doug Murray said
at a pair of open houses on Thursday at the Adventure Inn here.
Theres going to be huge spin-off to the economy, he remarked. Its
going to be a whole new industry.
Murray said the bio-mass boiler not only is expected to help keep the
650 mill employees, and some 350 forestry ones, on the job, but lead to more
employment for the region, whether its new jobs at the mill here, more
forestry jobs, or more jobs at sawmills supplying chip and bark for the
boiler.
For instance, the mill is expecting 40 or more extra trucks hauling
boiler fuel to town each day once the bio-mass boiler is operationalmeaning
more truck drivers will be needed.
But first, funding for the project has to be approved by the Abitibi
board of directors.
Manager John Harrison stressed why the bio-mass boiler is crucial to the
long-term viability of the local mill.
The pulp and paper-making processes are very energy intensive. So, two
major drivers of our mill's costs are steam and electricity, he noted.
As it is currently configured, the paper mill gets all its steam from
the co-gen plant with natural gas as the fuel supply, he explained. [But]
natural gas in North America has doubled in cost in the past six years,
doubling our steam cost.
Building the bio-mass boiler will allow us to generate this steam from
a cheaper renewable fuel source [wood residues], without reliance on natural
gas, he added.
That cheaper steam can also be used to generate less expensive
electricity in our steam turbine.
These two impacts combined will significantly reduce our costs and make
us competitive in the industry, said Harrison.
If the bio-mass boiler comes on line, however, the resulting energy
savings will make the local mill Abitibis lowest cost producers of glossy
and high bright grades.
If Abitibis board approves the project, boiler components will be
ordered from a vendor and an engineer hired this spring, with the final
approval of property rezoning going before the Ministry of Housing and
Municipal Affairs in June.
As soon as that happens, construction of the foundation will begin.
The steel framework of the bio-mass boiler building will get underway in
September, in anticipation of the boiler parts arriving in March, 2008
(there will be no winter construction on the site).
This will be followed by an intense period of construction of the
boiler, with a completion date of October, 2008.
The bio-mass boiler building would be situated at the south end of
Portage Avenue, across from the jail. Portage Avenuefrom Nelson to
Sinclairwould be closed off.
The boiler building will look roughly like the present recovery
building, standing about 120 feet high, while the boiler itself will be
about 26 feet deep and 34 feet wide.
Trucks will haul fuel to the wood yard, where it will be loaded onto a
conveyor system running to the bio-mass boiler. There, it will be burned,
releasing heat and, in turn, steam, which goes to a steam turbine generating
electricity.
The only waste product will be ash, which will be hauled away to the
landfill.
As the name implies, the bio-mass boiler will run on wood waste,
including harvest slash, bark, sawdust, and sludge.
While some of the fuel, such as sludge, will come from the mill, the
majority of the fuels will be hauled in from area woodlands or sawmills.
Other possible fuels, like straw pellets or bales, also may be
considered in the future. Murray noted the fuel value from agricultural
products is as high as it is from wood waste.
The bio-mass boiler will burn 1,000 dry tonnes of fuel per day, but the
ability to supply this has been accounted for in the proposal.
Were confident the fuel supply will be there for us, said Harrison.
When asked about pollution and noise produced by the boiler, Harrison
noted the bio-mass boiler should produce minimal noise and is expected to
fall well within Ministry of Environmental guidelines as far as emissions
go.
Not only is the success of the bio-mass boiler proposal the real key to
keep the mill viable here in Fort Frances, said Harrison, but also is the
key to a tentative agreement struck between the four local mill unions and
the company in early January.
The unions agreed to a contract extension to give the company some
long-term labour stability in exchange for a guarantee it would build and
operate a new bio-mass boiler here.