Sludge Watch ==> Hawksbury Ontario - violations of sewer laws, effluent, and sludge
Maureen Reilly
maureen.reilly at sympatico.ca
Mon May 26 16:56:24 EDT 2008
Sludgewatch Admin
This little Canadian town has less than 11,000 people. Lets see .. even a
low ball sewage plant renovation of $30M is about $3,500 per person.
Isn't it time to explore on site septic systems for these little towns?
Take some people off the big pipe...let them manage their own sanitary
wastes with commercialized on site systems.
...................................
TRIBUNE-EXPRESS - News
Town has broken provincial, municipal rules
May 23 2008
by richard.mahoney at eap.on.ca
The town of Hawkesbury has admitted that its sewage treatment plant is
breaking a provincial law, and that the municipality has not been enforcing
its own industrial sewage rules.
The town was fined $12,5000 in Provincial Offences Court in LâOrignal
after pleading guilty to one charge laid under the Ontario Water Resources
Act by the Ontario Ministry of the Environment. Ministry lawyer Paul
McCulloch suggested the $12,500 fine after he informed the court that the
ministry was withdrawing one charge, and amending another count.
Under the law, the town could have been fined anywhere from $25,000 to $6
million.
Outside court, McCulloch acknowledged that a factor in the fine amount was
the fact the town was spending a large amount of money to resolve the
problems that have dated back to 2005.
The solution to the townâs wastewater treatment woes could cost between
$26 million and $42 million. Under conventional cost-sharing deals with the
federal and provincial governments, municipalities are expected to pay
one-third of approved costs. In Hawkesburyâs case, taxpayers would be
faced with a bill of $9 million to $14 million.
An agreed statement of facts notes that between May 2005 and November 2006,
with the exception of May, 2006, the effluent from the water pollution
control plant exceeded permitted levels. Although the plant was operated by
the Ontario Clean Water Agency, the town retained overall responsibility for
the operation of the Main Street facility.
"The town had retained a consultant to find solutions which would permit the
water pollution control plant to operate within the parameters of the
certificate of approval. The potential solutions were not addressed in a
timely manner and the operation of the water pollution control plant was not
maximizing available biosolid management practices," the statement reads.
"A subsequent investigation determined that limited biosolids storage
capabilities and the discharge from a few industries into the townâs
sewers were contributing factors for the exceedances. The investigation
further confirmed that the town had not proceeded with installing further
approved equipment that was intended to address biosolids management and
that the town had failed to enforce its own by-law that controls the
discharge of sewage and/or industrial wastes into the sewage works system,"
the statement continues.
The ministry pointed out that the town has since retained the Thompson
Rosemount Group as consultants to help OCWA in biosolids management.
Improvements to biosolids disposal have been implemented at "significant
expense" to the municipality, the ministry told the court.
The municipality has also encouraged two industries to install on-site
treatment systems to pre-treat their industrial wastewater prior to
discharging it into the townâs sewers.
Meanwhile, the municipality has been presented two alternatives that call
for the expansion of the current installations, at a cost of $26.4 million
or $42.2 million. The most costly option would be necessary if the
government requires nitrification, the process which renders ammonia
non-toxic. The third option, constructing a new plant on the same site,
would cost $39.6 million.
At the end of an environmental assessment process, council will submit an
application for funds under a provincial-federal infrastructure program. The
town is effectively freezing new construction because the plantâs capacity
is almost exhausted. Although a sum of $6.8 million was spent on the plant
in 2006, the investment did not resolve all of the stationâs defects.The
standard "do nothing" option is not feasible. In addition to continued
problems meeting the effluent limits, continued challenges with the
hydraulic loading, and no extra capacity to service future growth in the
town, the town must spend approximately $3,000,000 on repairs and
replacement of equipment at the plant.
http://www.tribune-express.ca/nouvelles.asp?nID=11153
More information about the Sludgewatch-l
mailing list